The purpose of this Plan is to address the procedures and monitoring requirements for construction of the project. This Plan is intended to:
This procedure sets forth the construction quality program requirements that are to be applied to work performed by DAMASConstruction Institution (DCI). It is intended that thisQA program will meet the requirements of the DAMASConstruction Institution (DCI) Quality Policy as it relates to Construction Services. This QA/QC policy is also intended to ensure that all construction activities are performed in complete conformance with the approved construction drawings and all applicable standards, specifications and contract requirements.
The decision to implement this QA program for a particular construction job will be made at the sole discretion of the management of DAMASConstruction Institution (DCI).
The decision to implement this program (or any part of this program) for a particular job will be based on, but will not be limited to, the following criteria:
Each construction site shall have at least one DAMASConstruction Institution (DCI) QC representative or individual identified as the QA/QC contact. Depending on the construction site, this QA/QC function may be expanded to include additional personnel as dictated by the size of the project and/or scope of work activities. The organizational structure for the project shall be aligned in such a manner as to allow the onsite QC representative the necessary autonomy to perform the QA/QC function in an unbiased manner.
In addition, the onsite DAMASConstruction Institution (DCI) QC representative will work with the Corporate QC Coordinator to conduct periodic assessments of the overall QA/QC implementation for the project.
This section describes the scope of project management responsibility, authority and interrelationships.
Preparation of daily QA/QC documentation will consist of daily field reports prepared by the QA/QC Site Manager which may include QA/QC monitoring logs and testing data sheets. This information may be regularly submitted to and reviewed by the Construction Manager. Daily field reports will include documentation of the observed activities during each day of activity. The daily field reports may include monitoring logs and testing data sheets. At a minimum, these logs and data sheets will include the following information:
Construction Problems and Resolution Data Sheets, to be submitted with the daily field reports prepared by the QA/QC Site Manager, describing special construction situations, will be cross-referenced with daily field reports, specific observation logs, and testing data sheets and will include the following information, where available:
The Construction Manager will be made aware of significant recurring non-conformance with the Drawings, Technical Specifications, or QA/QC Plan. The cause of the non-conformance will be determined and appropriate changes in procedures or specifications will be recommended. These changes will be submitted to the Construction Manager for approval. When this type of evaluation is made, the results will be documented and any revision to procedures or specifications will be approved by the Contractor and Engineer.
A summary of supporting data sheets, along with final testing results and the
QA/QC Site Manager’s approval of the work, will be required upon completion of construction.
Photographs will be taken and documented in order to serve as a pictorial record of work progress, problems, and mitigation activities. These records will be presented to the Construction Manager upon completion of the project. Photographic reporting data sheets, where used, will be cross-referenced with observation and testing data sheet(s), and/or construction problem and solution data sheet(s).
Design and/or specifications changes may be required during construction.
In such cases, the CQA Site Manager will notify the Engineer. Design and/or specification changes will be made with the written agreement of the Engineer and will take the form of an addendum to the Drawings and Technical Specifications.
An internal audit in the field shall be performed to verify quality control activities are in accordance with written procedures and general provisions. The audit shall include but not limited to:
The quality inspector on site shall perform a continuous audit on a dat to day basis reporting any non-conformances in application of the QA/QC policy to the QA/QC manager. The quality inspector shall also investigate corrective procedures within his term of responsibility or inform the QA/QC manager accordingly for further action.
The QA/QC manager, project manager, and quality inspectors shall perform a minimum of three random audits at 10-20%, 50-60, and 80-90% completion of the work. The results of these audits are to be recorded for inspection by the client or his representative.Random audits shall be performed at any time especially when circumstances changes, such as major changes in the QA/QC policy, new personnel, and to verify corrective actions are properly performed and documented.
Audit shall be carried out according to checklists previously prepared to suit each particular case and activity or facility to be audited. A report shall be issued on completion of each audit giving a summary of the findings and recommendations for corrective action if necessary.
When corrective actions are recommended, the time limit for their implementation should be stated. The activity concerned should be audited again at the expiration of the time limit to verify correction of the identified non-conformance.
DAMASConstruction Institute (DCI) shall implement and maintain a document control system to ensure:
Overall responsibility for planning and control of the document control system for QA/QC matters shall be assigned to the QA/QC supervisor. He shall establish and maintain the following records and files. It shall be his responsibility to see these records are properly maintained and stored after project completion and that each of the subcontractors (if any) on this contract establish and maintain similar records.
A record of all tests field sequentially and by work categories. All tests including but not limited to the following shall be controlled and properly documented:
The following documents shall be controlled in accordance with this procedure:
The QA/QC inspector in conjunction with the site engineer shall check all purchasing documentation prior to dispatch to potential manufacturers, subcontractors and suppliers.
The goods, materials, equipment or work to be performed shall be checked with the following guidelines:
All material deliveries to the site shall be inspected and checked by QC inspector to ensure the materials are not damaged or defective and conforms to the material approvals, purchase orders, and packing lists.
A materials receipt checklists shall be used as guidelines in checking delivered products.
The purpose of this procedure is to outline the general guidelines necessary to insure that the quality of items received on DAMAS CONSTRUCTION INSTITUTE (DCI) construction projects is in compliance with manufacture’s literature, applicable codes, standards and specifications and is maintained throughout the receipt, storage and handling process.
Generally, items shall be received, stored and handled in accordance with the manufacturer’s recommendations. In addition, specific requirements listed in job site specifications shall be followed as they apply to items received on site. In lieu of recommendations and specifications, the guidelines listed in this procedure shall be followed.This procedure is an integral part of the DAMAS Construction Institute (DCI) Quality Assurance Program.
Responsibility
Generally, it will be the responsibility of DAMASConstruction Institute(DCI) to insure that items received on site are received, stored and handled in a manner that will maintain the quality of the items received. DAMASConstruction Institute(DCI) will perform whatever inspections are deemed necessary to insure the quality of items is being maintained.
Receiving Inspection Requirements
A preliminary visual inspection shall be performed prior to unloading to determine if any damage occurred during shipping and to insure compliance to the applicable purchase order. Observations shall be made for the following:
Any indication of the above conditions shall be brought to the attention of the appropriate discipline leads, preferably before unloading. Receipt, storage and handling requirements for specific items may be found in the particular discipline inspection procedures: Civil Inspection, Electrical Inspection, Mechanical Inspection and Welding Inspection.
After unloading, the following areas should also be checked:
Storage Requirements
Items shall be stored in a manner that will maintain the quality of the item and minimize the possibility of damage due to corrosion, contamination, deterioration or physical damage.
First and foremost, items shall be stored in accordance with manufacturer’s recommendations and job site specifications.
The purpose of this procedure is to outline the general guidelines necessary to assure that the civil construction activities performed on DAMASConstruction Institute(DCI) construction projects are performed in accordance with applicable codes, standards, specifications and drawings.
Scope
This procedure will cover general inspection criteria in the areas of: Soils Inspection, Reinforcing Steel Inspection, Concrete Inspection, Grouting Inspection, Structural Steel Inspection, Coatings Inspection, and Ductwork Inspection and Insulation.
Construction activities and subsequent inspection criteria shall be based on job site specifications, procedures and drawings. In lieu of jobsite specifications or where referenced by jobsite specifications, national codes and standards shall be used.
Responsibility
Generally, it will be the responsibility of DAMASConstruction Institute(DCI) to insure that construction activities are performed in accordance with applicable specifications, procedures, drawings, codes and standards. SCG DAMASConstruction Institute(DCI) shall perform whatever inspections and tests are deemed necessary to insure that construction activities are being performed in accordance with job requirements.
Earthwork construction activities shall be performed in accordance with job site specifications, procedures and drawings. Soils inspection shall be performed by qualified personnel who shall verify that requirements of the specifications, procedures and drawings are being met.
Reinforcing steel shall be received, stored and handled in accordance with procedure (Storage and Handling of Products). As part of the receipt inspection, mill test reports shall be checked and fabricated bars shall be randomly checked against the bar lists for compliance.
Key Inspection Attributes:
In addition to the receipt inspection items listed above, the following are minimum key inspection items that should be checked and or verified as a part of reinforcing steel inspection:
Key Inspection Attributes:
Following are key inspection items for each type of batch plant inspection:
Initial Inspection
Concrete Pre placement
Concrete pre placement construction activities shall consist of foundation preparation, rebar and embed placement, form construction and all other activities necessary to prepare for concrete placement.
Key Inspection Attributes
Following are minimum key inspection items that should be checked and/or verified prior to concrete placement:
Concrete placement activities shall consist of the actual placing of the concrete and all testing that is required on the fresh concrete prior to and during placement.
Key Inspection Attributes
Following are minimum key inspection items that should be checked and/or verified prior and during concrete placement:
Concrete post placement activities shall consist of application and maintenance of curing compound or other methods of curing, form removal, concrete repair and storage of concrete cylinders.
Key Inspection Attributes
Following are minimum key inspection items that should be checked and/or verified as part of concrete post placement activities:
Non shrink structural grout shall be shipped to the job site in bags and shall be received, stored and handled in accordance with procedure (Storage and Handling of Products).
Key Inspection Attributes
Following are minimum key inspection items that should be checked and/or verified as part of grout placement activities.
Structural steel, including high strength bolts, washers and nuts shall be received, stored and handled in accordance with procedure: Storage and Handling of Products. As a part of receipt inspection, individual members shall be randomly checked against the fabrication drawings via the piece number for compliance.
Erection
Structural steel erection, high strength bolting and welding processes shall be in accordance with job site specifications, procedures, and drawings; Daily activities should be recorded.
Prior to erecting steel, the steel erector shall be provided with documentation that shows that the concrete in the footings, piers and walls and the mortar in masonry piers and walls has attained either 75 percent of the intended minimum compressive design strength or sufficient strength to support the loads imposed during steel erection. In addition, the steel erector shall receive written notification of any repairs, replacements and modifications to the anchor bolts.
Key Inspection Attributes
Following are minimum key inspection items that should be checked and/or verified as part of structural steel erection activities:
Paints and coatings shall be received, stored and handled in accordance with procedure: Storage and Handling of Products. A Materials Safety Data Sheet shall be on site for each type of coatings received and should be reviewed by the appropriate personnel before the start of work.
Paint and/or coatings shall be applied in accordance with job site specifications, procedures, drawings and manufacturer’s recommendations. Daily activities should be recorded.
Key Inspection Attributes
Following are minimum key inspection items that should be checked and/or verified as part of paints and coatings application activities:
Wet Film Thickness Readings
Dry Film Thickness Readings
Ductwork components shall be received, stored and handled in accordance with
Procedure: Storage and Handling of Products.
Ductwork components shall be assembled in accordance with job site specifications, procedures, drawings and manufacturer’s recommendations. Daily activities should be recorded.
Key Inspection Attributes
Following are minimum key inspection items that should be checked and/or verified as part of ductwork assembly activities:
Purpose
This procedure establishes guidelines for the construction and installation inspection of electrical components at DAMASConstruction Institute(DCI) construction projects.
Scope
Electrical components covered under this procedure shall include, but not limited to, grounding systems, embedded items, raceway and cable tray systems, cable installation and termination, and electrical equipment. In lieu of manufacturer’s recommendations and specifications, the guidelines in this procedure shall be followed.
Responsibility
It is the responsibility of DAMASConstruction Institute (DCI) to ensure that electrical equipment is received, stored, maintained, handled and installed in a manner that will ensure the quality of equipment. Whatever inspections shall be performed to ensure the quality of items being installed has been maintained.
DAMASConstruction Institute(DCI) is responsible for coordinating work activities with other disciplines involved in electrical discipline installations. And will ensure all deficiencies have been resolved.
Construction Systems
Storage and Handling of Electrical Equipment
When electrical equipment has been received and placed in its designated area, all documentation and storage requirements will be performed as recommended by the manufacturer. Some key inspection attributes include but are not limited to the following:
Cable Installation
Power, control and telecommunication conductors are essential for any plant.
Proper installation techniques will limit stress damage to conductors and reduce operational testing requirements of the conductor over its service life. Some key inspection attributes include but are not limited to the following:
Equipment Installation
Equipment installation includes but is not limited to rotating equipment, enclosures, transformers and other associated equipment. Proper installation techniques are mandatory to ensure equipment functions as intended. Equipment checks will verify equipment location, orientation, configuration, supports and anchoring systems are in accordance with site specifications.
Equipment and system testing will ensure equipment will function during start up and operational phases. As a minimum, a check will be made to verify all electrical equipment has been installed in accordance with site drawings, specifications and manufacturer recommendations. Some key inspection attributes include but are not limited to the following:
Purpose
The purpose of this procedure is to outline the general guidelines necessary for the inspections of mechanical equipment, piping systems, piping support structures, instrumentation, valves, insulation and lagging, and hydrostatic testing at DAMASConstruction Institute(DCI) construction projects.
Scope
Mechanical equipment covered under this procedure shall include, but not be limited to, motorized and non-motorized valves, pumps, compressors, tanks, heat exchangers, fired and unfired vessels, filter vessels, in line components (expansion joints, etc.) and other equipment that is within the mechanical inspection scope of work.
Generally, mechanical equipment, piping, piping support structures, in line components, instrumentation, valves, and insulation and lagging should be received, stored, maintained and installed in accordance with manufacturer’s recommendations and mechanical engineering practices. In addition, specific requirements listed in project specifications and drawings shall be followed. In lieu of manufacturer’s recommendations and specifications, the guidelines in this procedure should be followed.
Responsibility
Generally, it will be the responsibility DAMASConstruction Institute(DCI) to ensure that mechanical equipment, piping, piping supports, in line components, instrumentation, valves, insulation and lagging are received, stored, maintained, handled, and installed in a manner that will ensure the
quality of equipment received. Inspections and tests shall be performed as deemed necessary to ensure that the quality of items is maintained.
Mechanical Equipment Maintenance Requirements
When mechanical equipment has been received and all preliminary inspections have been performed, couplings for driven equipment that are not installed, (loosely attached to the equipment), should be removed, packaged, tagged and placed in storage until equipment installation prior to equipment turnover. Inspection personnel should complete a maintenance checklist (refer to sample forms for an example) and update same as needed until equipment has been released to plant operations personnel.
Piping Systems Inspection
When inspecting piping systems the following items should be checked:
Purpose
The purpose of this procedure is to outline the general guidelines for the visual inspection of welding performed at DAMASConstruction Institute(DCI) construction projects.
Scope
This procedure is an integral part of the DAMASConstruction Institute(DCI) QualityAssurance Program and is intended for use on DAMASConstruction Institute(DCI) construction projects.
Responsibility
Generally, it will be the responsibility of DAMASConstruction Institute(DCI) to ensure that welding is performed according to the applicable section of the governing codes, approved welding procedure specifications, and project specifications and drawings.
Inspections shall be performed ranging from random observations to total weld inspection as deemed necessary to ensure weld quality.The degree of weld inspection will be based on the structural significance, prior experience, and past observations.
Visual Welding Inspection
DAMASConstruction Institute(DCI) shall insure that welders and welding operators are qualified in the process being performed. If applicable, inspection personnel will be aware of any welder retest dates and welder’s symbols. Inspection personnel shall be responsible for preparing and maintaining a Visual Weld Inspection Report as needed for inspected welds at project locations.
As required, inspection personnel shall monitor the welding process during the following stages for compliance to codes and specifications.
Acceptance Criteria
The acceptance criteria for all welding performed on DAMASConstruction Institute(DCI) construction projects will be controlled by the applicable section of the governing code, and project specifications and drawings. In general, inspection personnel should also verify that:
Welding Machines
All machines being used for welding shall be in satisfactory working condition and set at
WPS nominal amperages required to maintain a stable arc for the type and size of electrode, welding position, and particular weld joint configuration. Any unsafe conditions such as worn leads, tripping hazards, electrical shock, or fire hazards shall be noted and reported to the appropriate personnel.
Base Material Composition
Welding procedure specifications (WPS) shall be referenced to verify the required base material composition for weld elements. Base material composition may be assessed by checking manufacturer mill test reports or purchase orders. Any base metal imperfections or deviations should be noted and/or rectified prior to welding.
Weld Repair/Rework
It is important that construction not progress to the point that welds cannot be inspected.
Inspection personnel shall be notified in a timely manner in order to inspect completed welds while the welds are still accessible. For welds that have unacceptable discrepancies and repair/rework is required, work shall be performed to the same specifications as the original weld (unless there is special engineering documentation to change processes). The completed weld shall meet the same acceptance standards as the original weld. Welds found unacceptable shall be noted on the Visual Inspection Report stating the reason(s) for rejection. When the repaired/reworked weld has been found acceptable, the Visual Inspection Report shall be updated to verify acceptance.